The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has parkway restoration to complete in various locations where the storm sewer work has been completed.

The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.