Thursday, April 21, 2011

The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has storm sewer work and hot-mix asphalt patching to complete on Harrison and Pebbleford late this week or early next week.

The contractor is scheduled to resume storm sewer work on Mary Kay Lane and Pebbleford Lane late this week or early next week. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.