Thursday, November 3, 2011

Friday, October 28, 2011

This project is nearing completion with only punch list work remaining.

Wednesday, October 19, 2011

This project is nearing completion with only punch list work remaining.

Friday, October 14, 2011

This project is nearing completion with only punch list work remaining.

Friday, October 7, 2011

DiMeo Bros. installed the backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue) this week. This project is nearing completion with only punch list work remaining.

Friday, September 30, 2011

This project is nearing completion with only punch list work and the installation of backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue).

Friday, September 23, 2011

This project is nearing completion with only punch list work and the installation of backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue).

Friday, September 16, 2011

This project is nearing completion with only punch list work and the installation of backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue).

Friday, September 9, 2011

This project is nearing completion with only punch list work and the installation of backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue).

Friday, September 2, 2011

DiMeo Bros. is scheduled to work on the drainage improvements (storm overflow route) off of Pebbleford Lane this week. This project is nearing completion with only punch list work and the installation of backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue).

Friday, August 26, 2011

This project is nearing completion with only punch list work, drainage improvements (storm overflow route) off of Pebbleford, and the installation of backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue).

Friday, August 19, 2011

This project is nearing completion with only punch list work, drainage improvements (storm overflow route) off of Pebbleford, and the installation of a backflow prevention device in the storm sewer off of Harrison Street (at Flora Avenue).

Friday, August 12, 2011

This project is nearing completion with only punch list work, drainage improvements (storm overflow route) off of Pebbleford, and the installation of backflow prevention devices in the storm sewer off of Pine Street and Harrison Street (at Flora Avenue).

Friday, August 5, 2011

This project is nearing completion with only punch list work, drainage improvements (storm overflow route) off of Pebbleford, and the installation of backflow prevention devices in the storm sewer off of Pine Street and Harrison Street (at Flora Avenue).

Friday, July 29, 2011

This project is nearing completion with only punch list work, drainage improvements (storm overflow route) off of Pebbleford, and the installation of backflow prevention devices in the storm sewer off of Pine Street and Harrison Street (at Flora Avenue).

Friday, July 22, 2011

This project is nearing completion with only restoration work, punch list work and the installation of backflow prevention devices at various locations in the storm sewer remaining. Next week, the contractor is scheduled to work on restoration on Pine Street. The contractor is also scheduled to work on the drainage improvements (storm overflow route) off of Pebbleford next week.

Friday, July 15, 2011

This project is nearing completion with only punch list work and the installation of backflow prevention devices at various locations in the storm sewer remaining.

Friday, July 8, 2011

DiMeo Bros. has completed the storm sewer work on Pine Street this week. This week and next week, the contractor is scheduled to complete the pavement and parkway restoration work on Pine Street.

Thursday, June 30, 2011

DiMeo Bros. is working to complete the storm sewer work on Pine Street this week. Next week, a concrete contractor will be completing driveway and curb and gutter replacement and constructing the flared end section outfall at the river bank.

Friday, June 24, 2011

DiMeo Bros. is working to complete the storm sewer work on Pine Street next week.

Thursday, June 16, 2011

DiMeo Bros. has started the storm sewer work on Pine Street this week and is scheduled to continue this work into next week.

Friday, June 10, 2011

DiMeo Bros. has completed the storm sewer installation on Harrison and Flora this week. An asphalt contractor is scheduled to complete pavement patching at Harrison and Flora through the Minor Area Repair Strategy (MARS) program possibly next week.

DiMeo Bros. is scheduled to begin the storm sewer work on Pine Street next week.

Friday, June 3, 2011

DiMeo Bros. has resumed with the storm sewer installation on Harrison and Flora now that the conflict with the gas main is resolved.

DiMeo Bros. is in the process of scheduling the storm sewer work with the Village on Pine Street now that the utility easements are in place.

Friday, May 27, 2011

Nicor Gas has finished the relocation of the gas mains in conflict with
the proposed storm sewer on Harrison Street and Flora Avenue this week.
DiMeo Bros. is scheduled to complete the storm sewer work on Harrison
Street and Flora Avenue next week.

DiMeo Bros. will complete the storm sewer work on Pine Street once the
utility easements are in place.

Monday, May 9, 2011

The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and landscaping at the locations where storm sewer has been completed.

The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.

Saturday, April 30, 2011

The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has parkway restoration to complete in various locations where the storm sewer work has been completed.

The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.

Thursday, April 21, 2011

The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has storm sewer work and hot-mix asphalt patching to complete on Harrison and Pebbleford late this week or early next week.

The contractor is scheduled to resume storm sewer work on Mary Kay Lane and Pebbleford Lane late this week or early next week. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.

Friday, April 15, 2011

DiMeo Bros. has completed the curb and gutter restoration, pavement patching, sidewalk replacement and started landscaping restoration this week in various locations where storm sewer has been completed. Additionally, DiMeo Bros. completed the installation of storm sewer at West Lake Street and Lehigh Avenue.

Next week, DiMeo Bros. is scheduled to continue with pavement patching and landscaping restoration in various locations where storm sewer has been completed. Additionally, DiMeo Bros. will resume storm sewer work on Mary Kay Lane and Pebbleford Lane next week.

Friday, April 8, 2011

DiMeo Bros. will begin curb and gutter restoration next week in various locations where storm sewer has been completed south of West Lake Avenue, as well as at Cambridge north of West Lake Avenue.

Friday, April 1, 2011

Work on Harrison Street and Flora Street is on hold due to water main and gas main conflicts. Storm Sewer work on Pfingsten Road and Knight is scheduled to take place next week.

Wednesday, March 23, 2011

Storm sewer work is starting on Harrison Street and Flora Avenue this week and will continue into next week.

Thursday, March 17, 2011

Construction continues.

Storm sewer work is ongoing on Pebbleford Lane and Mary Kay Lane this week and will continue into next week. Upon completion of Pebbleford Lane and Mary Kay Lane the Contractor will move to Harrison Street and Flora Avenue.