Friday, October 7, 2011
Friday, September 30, 2011
Friday, September 23, 2011
Friday, September 16, 2011
Friday, September 9, 2011
Friday, September 2, 2011
Friday, August 26, 2011
Friday, August 19, 2011
Friday, August 12, 2011
Friday, August 5, 2011
Friday, July 29, 2011
Friday, July 22, 2011
This project is nearing completion with only restoration work, punch list work and the installation of backflow prevention devices at various locations in the storm sewer remaining. Next week, the contractor is scheduled to work on restoration on Pine Street. The contractor is also scheduled to work on the drainage improvements (storm overflow route) off of Pebbleford next week.
Friday, July 15, 2011
Friday, July 8, 2011
Thursday, June 30, 2011
Friday, June 24, 2011
Thursday, June 16, 2011
Friday, June 10, 2011
DiMeo Bros. has completed the storm sewer installation on Harrison and Flora this week. An asphalt contractor is scheduled to complete pavement patching at Harrison and Flora through the Minor Area Repair Strategy (MARS) program possibly next week.
DiMeo Bros. is scheduled to begin the storm sewer work on Pine Street next week.
DiMeo Bros. is scheduled to begin the storm sewer work on Pine Street next week.
Friday, June 3, 2011
Friday, May 27, 2011
Nicor Gas has finished the relocation of the gas mains in conflict with
the proposed storm sewer on Harrison Street and Flora Avenue this week.
DiMeo Bros. is scheduled to complete the storm sewer work on Harrison
Street and Flora Avenue next week.
DiMeo Bros. will complete the storm sewer work on Pine Street once the
utility easements are in place.
the proposed storm sewer on Harrison Street and Flora Avenue this week.
DiMeo Bros. is scheduled to complete the storm sewer work on Harrison
Street and Flora Avenue next week.
DiMeo Bros. will complete the storm sewer work on Pine Street once the
utility easements are in place.
Monday, May 9, 2011
The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and landscaping at the locations where storm sewer has been completed.
The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.
The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.
Saturday, April 30, 2011
The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has parkway restoration to complete in various locations where the storm sewer work has been completed.
The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.
The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.
Thursday, April 21, 2011
The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has storm sewer work and hot-mix asphalt patching to complete on Harrison and Pebbleford late this week or early next week.
The contractor is scheduled to resume storm sewer work on Mary Kay Lane and Pebbleford Lane late this week or early next week. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.
The contractor is scheduled to resume storm sewer work on Mary Kay Lane and Pebbleford Lane late this week or early next week. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.
Friday, April 15, 2011
DiMeo Bros. has completed the curb and gutter restoration, pavement patching, sidewalk replacement and started landscaping restoration this week in various locations where storm sewer has been completed. Additionally, DiMeo Bros. completed the installation of storm sewer at West Lake Street and Lehigh Avenue.
Next week, DiMeo Bros. is scheduled to continue with pavement patching and landscaping restoration in various locations where storm sewer has been completed. Additionally, DiMeo Bros. will resume storm sewer work on Mary Kay Lane and Pebbleford Lane next week.
Next week, DiMeo Bros. is scheduled to continue with pavement patching and landscaping restoration in various locations where storm sewer has been completed. Additionally, DiMeo Bros. will resume storm sewer work on Mary Kay Lane and Pebbleford Lane next week.
Friday, April 8, 2011
Friday, April 1, 2011
Wednesday, March 23, 2011
Thursday, March 17, 2011
Construction continues.
Storm sewer work is ongoing on Pebbleford Lane and Mary Kay Lane this week and will continue into next week. Upon completion of Pebbleford Lane and Mary Kay Lane the Contractor will move to Harrison Street and Flora Avenue.
Subscribe to:
Posts (Atom)