Friday, May 27, 2011

Nicor Gas has finished the relocation of the gas mains in conflict with
the proposed storm sewer on Harrison Street and Flora Avenue this week.
DiMeo Bros. is scheduled to complete the storm sewer work on Harrison
Street and Flora Avenue next week.

DiMeo Bros. will complete the storm sewer work on Pine Street once the
utility easements are in place.

Monday, May 9, 2011

The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and landscaping at the locations where storm sewer has been completed.

The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.