Friday, July 29, 2011

This project is nearing completion with only punch list work, drainage improvements (storm overflow route) off of Pebbleford, and the installation of backflow prevention devices in the storm sewer off of Pine Street and Harrison Street (at Flora Avenue).

Friday, July 22, 2011

This project is nearing completion with only restoration work, punch list work and the installation of backflow prevention devices at various locations in the storm sewer remaining. Next week, the contractor is scheduled to work on restoration on Pine Street. The contractor is also scheduled to work on the drainage improvements (storm overflow route) off of Pebbleford next week.

Friday, July 15, 2011

This project is nearing completion with only punch list work and the installation of backflow prevention devices at various locations in the storm sewer remaining.

Friday, July 8, 2011

DiMeo Bros. has completed the storm sewer work on Pine Street this week. This week and next week, the contractor is scheduled to complete the pavement and parkway restoration work on Pine Street.