Saturday, April 30, 2011

The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has parkway restoration to complete in various locations where the storm sewer work has been completed.

The contractor will complete the storm sewer work on Pine Street once the utility easements are in place. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.

Thursday, April 21, 2011

The contractor has completed a majority of the hot-mix asphalt pavement patching, curb and gutter replacement and restoration at the locations where storm sewer has been completed. The contractor has storm sewer work and hot-mix asphalt patching to complete on Harrison and Pebbleford late this week or early next week.

The contractor is scheduled to resume storm sewer work on Mary Kay Lane and Pebbleford Lane late this week or early next week. The contractor will resume with the storm sewer installation on Harrison and Flora once the conflict with the gas main is resolved.

Friday, April 15, 2011

DiMeo Bros. has completed the curb and gutter restoration, pavement patching, sidewalk replacement and started landscaping restoration this week in various locations where storm sewer has been completed. Additionally, DiMeo Bros. completed the installation of storm sewer at West Lake Street and Lehigh Avenue.

Next week, DiMeo Bros. is scheduled to continue with pavement patching and landscaping restoration in various locations where storm sewer has been completed. Additionally, DiMeo Bros. will resume storm sewer work on Mary Kay Lane and Pebbleford Lane next week.

Friday, April 8, 2011

DiMeo Bros. will begin curb and gutter restoration next week in various locations where storm sewer has been completed south of West Lake Avenue, as well as at Cambridge north of West Lake Avenue.

Friday, April 1, 2011

Work on Harrison Street and Flora Street is on hold due to water main and gas main conflicts. Storm Sewer work on Pfingsten Road and Knight is scheduled to take place next week.